Large Projects – Multi-Department Review (+/- 30 Days for Initial Plan Review Letter)

Large-sized home projects often require Multi-Department Review (e.g., Engineering, Fire, Public Works) before a building permit can be issued. An initial Plan Review Letter is usually issued +/- 30 Days. The Plan Review Letter will outline any additional requirements and next steps.

Large home projects are typically characterized as:

  • Additions, major repairs involving extensive structural components.
  • Major repairs involving extensive structural components

More complex projects will require +/- 35 Days for initial Plan Review Letter to be issued.

  • New homes.
  • Major remodels involving extensive structural upgrades.

Next Steps

If you think your project qualifies for Multi-Department Review, complete the Building Permit Application and submit it with applicable supporting documents to the Planning & Building Department.